Forskjell mellom versjoner av «Vakuum bord til Shopbot»
Hopp til navigering
Hopp til søk
| (3 mellomliggende revisjoner av samme bruker vises ikke) | |||
| Linje 1: | Linje 1: | ||
| − | + | ==Parts available== | |
| − | + | # CNC-plus VT-4070 board (hanging on the wall) - https://cnc-plus.de/en/Workholding/vacuum-clamping-tables/VT-4070-Vacuum-Table--Vacuum-Clamping-Plate-400x700mm-.html | |
| − | + | # CNC-plus VT-4070 tubes (in a transparent box under Shopbot) | |
| + | # Becker KVT 3.100 Vacuum Pump(under Shopbot) - https://www.becker-international.com/de/en/products/vacuum-pumps/rotary-vane-vacuum-pumps-oil-free/kvt3.100.htm | ||
| + | |||
| + | ==Process== | ||
# Mount the VT-4070 board. Use the mounting holes it has. | # Mount the VT-4070 board. Use the mounting holes it has. | ||
# Connect the tubes to the vacuum pump | # Connect the tubes to the vacuum pump | ||
# Connect the 3-phase power cable of the vacuum pump (long cable) | # Connect the 3-phase power cable of the vacuum pump (long cable) | ||
| − | # Place your material. Make sure | + | # Place your material (there are dowel pins that match the board in the tubes box). Make sure area that is not used is covered. |
# Start the vacuum pump. Test good suction is in place. It is your responsibility to make sure enough suction is available. | # Start the vacuum pump. Test good suction is in place. It is your responsibility to make sure enough suction is available. | ||
| − | # Start milling. | + | # Start milling (or cutting with the drag knife you can find in the tubes box). |
Nåværende revisjon fra 27. aug. 2026 kl. 14:13
Parts available
- CNC-plus VT-4070 board (hanging on the wall) - https://cnc-plus.de/en/Workholding/vacuum-clamping-tables/VT-4070-Vacuum-Table--Vacuum-Clamping-Plate-400x700mm-.html
- CNC-plus VT-4070 tubes (in a transparent box under Shopbot)
- Becker KVT 3.100 Vacuum Pump(under Shopbot) - https://www.becker-international.com/de/en/products/vacuum-pumps/rotary-vane-vacuum-pumps-oil-free/kvt3.100.htm
Process
- Mount the VT-4070 board. Use the mounting holes it has.
- Connect the tubes to the vacuum pump
- Connect the 3-phase power cable of the vacuum pump (long cable)
- Place your material (there are dowel pins that match the board in the tubes box). Make sure area that is not used is covered.
- Start the vacuum pump. Test good suction is in place. It is your responsibility to make sure enough suction is available.
- Start milling (or cutting with the drag knife you can find in the tubes box).